Latest / Before you drive

Roads Under Construction and Planned in Ehime, and When They Open (October 2026)Imabari Road Is "Scheduled to Open in Fiscal Reiwa 8"; No Timing Announced for the Ozu-Yawatahama Expressway, Tsushima Road or the Matsuyama Outer Ring Road

For drivers in Ehime. A list of the motorways, national route bypasses and four-lane widening sections under construction or planned in the prefecture, checked on the official pages of the Ministry of Land, Infrastructure, Transport and Tourism, Ehime Prefecture and NEXCO West Japan. Opening plans are given only where they are officially published. Includes the sections completed in 2025, and official figures and a map.

A viaduct of the Matsuyama Expressway
Matsuyama ExpresswayPhoto: CT-May / Wikimedia Commons (CC0)

Summary

  • MLIT says Imabari Asakura IC to Imabari Yunoura IC (5.7 km) on Imabari Road is "令和8年度 開通予定" (scheduled to open in fiscal 2026).
  • For Tsushima Road, the Ozu-Yawatahama Expressway and the rest of the Matsuyama Outer Ring Road, no announced opening timing was found.
  • The Shin-Uchiumi Tunnel (tentative name, 2,541 m) on Tsushima Road broke through on October 15, 2026.
  • The only 2025-2026 opening confirmed was the four-lane widening of a 6.3 km part of Iyo IC to Uchiko-Ikazaki IC on the Matsuyama Expressway.
  • MLIT says the partial opening of the Outer Ring Road Airport Line cut the time from Matsuyama IC to Matsuyama Airport from about 28 minutes to about 13.

List of Roads Under Construction and Planned (as of October 20, 2026)

This article was put together on October 20, 2026, from the official pages of the Ministry of Land, Infrastructure, Transport and Tourism (MLIT) (the Matsuyama River and National Highway Office and the Ozu River and National Highway Office), Ehime Prefecture and NEXCO West Japan. Opening plans are given only where an official fiscal year or similar timing is published. Where none is published, the table says “Not announced.” “Not announced” means that no announcement of the timing was found on official pages up to October 20, 2026.

Road Section Stage Planned opening Source
Imabari Road (今治道路) (Imabari-Komatsu Expressway, National Route 196) Imabari IC (今治IC) to Imabari Yunoura IC (今治湯ノ浦IC) (10.3 km) Under construction (project started in fiscal 2001) Imabari Asakura IC (今治朝倉IC) to Imabari Yunoura IC (5.7 km): “令和8年度 開通予定” (scheduled to open in fiscal Reiwa 8 (fiscal 2026)). Imabari IC to Imabari Asakura IC (4.6 km): not announced Matsuyama River and National Highway Office
National Route 11 Kawanoe-Mishima Bypass (川之江三島バイパス) Kawanoe-cho, Shikokuchuo to Nakanosho-cho (10.1 km) Partly open. Survey and design for the unopened sections Not announced Matsuyama River and National Highway Office
National Route 11 Niihama Bypass (新居浜バイパス) Funaki, Niihama to Ojoin (9.3 km) Partly open. Survey and design, land acquisition Not announced Matsuyama River and National Highway Office
National Route 11 Komatsu Bypass (小松バイパス) Komatsu-cho Shinyashiki, Saijo to Yasui (7.5 km) 2.4 km open with a provisional two lanes. Survey and design, land acquisition Not announced Matsuyama River and National Highway Office
Matsuyama Outer Ring Road (松山外環状道路) Airport Line (空港線) (National Route 56) National Route 56 to the Matsuyama Airport Line (a major local road) (3.8 km) Yogominami IC (余戸南IC) to Higashi-Habu IC (東垣生IC) (2.4 km) and the side roads (3.2 km) are open. The rest is under construction Not announced Matsuyama River and National Highway Office
Matsuyama Outer Ring Road Interchange East Line (インター東線) National Route 33 to National Route 11 (2.0 km; 2.5 km on the prefecture’s page) Project under way Not announced Matsuyama River and National Highway Office, Ehime Prefecture
Matsuyama Outer Ring Road (Matsuyama Airport to National Route 196) The section north of Matsuyama Airport Under study Not announced Ehime Prefecture
Four-lane widening of the Matsuyama Expressway Parts of Iyo IC (伊予IC) to Uchiko-Ikazaki IC (内子五十崎IC) and Uchiko-Ikazaki IC to Ozu IC (大洲IC) 6.3 km completed on April 19, 2025. The rest is in construction or design Not announced for the remaining sections NEXCO West Japan, Ehime Prefecture
Ozu-Yawatahama Expressway (大洲・八幡浜自動車道) Yoruhiru Road (夜昼道路) (National Route 197) Go, Yawatahama to Hirano, Ozu (4.2 km) Being built (since fiscal 2013) Not announced Ehime Prefecture
Ozu-Yawatahama Expressway Ozu-Nishi Road (大洲西道路) (National Route 197) Hirano, Ozu to Kitatada, Ozu (3.3 km) Being built (since fiscal 2017) Not announced Ehime Prefecture
Tsushima Road (津島道路) (National Route 56) Tsushima-Iwamatsu IC (津島岩松IC) to Uchiumi IC (tentative name) (内海IC(仮称)) (10.3 km) Under construction (project started in fiscal 2012) Not announced Ozu River and National Highway Office, Ehime Prefecture
Sukumo-Uchiumi Road (宿毛内海道路) (National Route 56) Sukumo-Wada IC (宿毛和田IC) to Uchiumi IC (tentative name) (29.2 km) Project approved (section by section, in fiscal 2022 and fiscal 2024) Not announced Ozu River and National Highway Office, Ehime Prefecture

The fiscal years in the Stage column are the fiscal years written on the prefecture’s and the national government’s pages and pamphlets, converted to the Western calendar. For the Ozu-Yawatahama Expressway, “since fiscal 2013” and “since fiscal 2017” are “H25〜” and “H29〜” in the prefecture’s pamphlet.

Ehime Prefecture describes the sections of the expressways in the prefecture that are not yet connected as follows.

本県における高速道路ネットワークの「3つのミッシングリンク」(「四国8の字ネットワーク」、「今治小松自動車道」、「大洲・八幡浜自動車道」の未整備区間)を早期に解消し、国土強靭化や地域経済の活性化、広域交流・連携の基盤となる道路ネットワークを形成するため、高規格道路の整備促進に努めています。

Translation: “To resolve at an early date the ‘three missing links’ in this prefecture’s expressway network (the unbuilt sections of the ‘Shikoku 8-shaped Network,’ the ‘Imabari-Komatsu Expressway’ and the ‘Ozu-Yawatahama Expressway’), and to form a road network that is a base for national resilience, revitalizing the regional economy, and wide-area exchange and cooperation, we are working to promote the building of high-standard roads.”

The Shikoku 8-shaped Network is a 798 km network of expressways made up of the Shikoku Jukan Expressway, the Shikoku Odan Expressway, the Kochi Tobu Expressway and the Anan-Aki Expressway. On the prefecture’s page, the completion rate as of April 1, 2025 is about 77%. In the figure in the prefecture’s pamphlet, the parts drawn as the missing links of the 8-shaped network are Tsushima Road, south of Uwajima City, and the Sukumo-Uchiumi Road, which runs from Uchiumi through Misho and Ipponmatsu to Sukumo Shinko (宿毛新港).

Figure of Ehime Prefecture’s three missing links: the Ozu-Yawatahama Expressway, the Imabari-Komatsu Expressway, and Tsushima Road and the Sukumo-Uchiumi Road on the Shikoku 8-shaped Network
Source: the figure cut out from “高規格道路 ~ミッシングリンクの解消~” (High-standard roads: resolving the missing links) on the front side of “愛媛の道路2025” (Ehime’s Roads 2025), Ehime Prefecture (PDF, in Japanese). The “R8年度開通予定” (scheduled to open in fiscal Reiwa 8) for Imabari Road is how this pamphlet put it at the time; it is posted on a page updated on June 26, 2025. Tap the image to open it larger.

Where the Main Sections Are

The points on the map are opened entrances and exits (ICs) and the place names at the start of the bypasses. The sections under construction themselves are not drawn as lines on the map. Entrances and exits that have not opened yet, such as Imabari Asakura IC, Ozu-Hirano IC and Uchiumi IC (tentative name), are not shown as points either.

Start and end points of roads under construction and planned, and nearby ICs

The numbers match the list below and are not a driving order. Tap a number on the map, or "Navigate in Google Maps" in the list, to start directions to that place.
Point locations: © OpenStreetMap contributors (ODbL), GSI place name search

  1. Imabari IC (今治IC): Near the start of Imabari Road (10.3 km). No opening timing has been announced for Imabari IC to Imabari Asakura IC (4.6 km).Navigate in Google Maps
  2. Imabari Yunoura IC (今治湯ノ浦IC): Near the end of Imabari Road. Imabari Asakura IC to Imabari Yunoura IC (5.7 km) is "令和8年度 開通予定" (scheduled to open in fiscal 2026) (Matsuyama River and National Highway Office).Navigate in Google Maps
  3. Kawanoe-cho, Shikokuchuo (四国中央市川之江町) (start of the Kawanoe-Mishima Bypass): A representative point of Kawanoe-cho, Shikokuchuo, the place name at the start of the National Route 11 Kawanoe-Mishima Bypass (10.1 km). It ends at Nakanosho-cho.Navigate in Google Maps
  4. Funaki, Niihama (新居浜市船木) (start of the Niihama Bypass): A representative point of Funaki, Niihama, the place name at the start of the National Route 11 Niihama Bypass (9.3 km). It ends at Ojoin.Navigate in Google Maps
  5. Komatsu-cho Shinyashiki, Saijo (西条市小松町新屋敷) (start of the Komatsu Bypass): A representative point of the place name at the start of the National Route 11 Komatsu Bypass (7.5 km). It ends at Komatsu-cho Yasui.Navigate in Google Maps
  6. Higashi-Habu IC (東垣生IC): The airport-side entrance and exit of the section of the Matsuyama Outer Ring Road Airport Line that opened on February 24, 2024. Beyond here toward the airport is under construction.Navigate in Google Maps
  7. Yogominami IC (余戸南IC): The Matsuyama IC-side entrance and exit of the section of the Matsuyama Outer Ring Road Airport Line that opened on February 24, 2024 (Yogominami IC to Higashi-Habu IC).Navigate in Google Maps
  8. Matsuyama IC (松山IC): In the pamphlet’s figure, the Matsuyama Outer Ring Road Interchange Line connects with the Matsuyama Expressway at Matsuyama JCT near here. The Interchange East Line (National Route 33 to National Route 11) is a project under way.Navigate in Google Maps
  9. Nakayama Smart IC (中山スマートIC): In the prefecture’s pamphlet figure, the 6.3 km whose four-lane widening was completed on April 19, 2025 (Futami-cho Kaminada to Miaki, Iyo) is near this IC.Navigate in Google Maps
  10. Uchiko-Ikazaki IC (内子五十崎IC): Four-lane widening construction and design continue on parts of Iyo IC to Uchiko-Ikazaki IC and Uchiko-Ikazaki IC to Ozu IC.Navigate in Google Maps
  11. Yawatahama East IC (八幡浜東IC): The Ozu-side end of the opened section of the Ozu-Yawatahama Expressway. From here to Hirano, Ozu is Yoruhiru Road (4.2 km, being built).Navigate in Google Maps
  12. Ozu-Kitatada IC (大洲北只IC): Ozu-Nishi Road (3.3 km, being built) runs from Hirano, Ozu to Ozu-Kitatada JCT (tentative name) around here.Navigate in Google Maps
  13. Tsushima-Iwamatsu IC (津島岩松IC): The southern end of Uwajima Road. From here to Uchiumi IC (tentative name) in Ainan Town is Tsushima Road (10.3 km, under construction).Navigate in Google Maps
  14. Kashiwa, Ainan (愛南町柏) (the district of the Shin-Uchiumi Tunnel construction site): The construction site of the Shin-Uchiumi Tunnel (tentative name, 2,541 m) is Kashiwa, Ainan to Tsushima-cho Kamihataji, Uwajima. The point is a representative point of the Kashiwa district, not the position of the tunnel.Navigate in Google Maps

Toyo: Imabari Road and Three Bypasses on National Route 11

Imabari Road: Imabari Asakura IC to Imabari Yunoura IC Is “Scheduled to Open in Fiscal Reiwa 8”

Imabari Road is a 10.3 km motorway that connects Imabari IC on the Shimanami Kaido and Imabari Yunoura IC on the Imabari-Komatsu Expressway. The Matsuyama River and National Highway Office is building it. The 13 km from Imabari Yunoura IC to Iyo-Komatsu JCT (いよ小松JCT) opened in July 2001.

The Imabari Road page of the Matsuyama River and National Highway Office says “令和8年度 開通予定” (scheduled to open in fiscal Reiwa 8 (fiscal 2026)) for Imabari Asakura IC to Imabari Yunoura IC. Fiscal Reiwa 8 runs from April 2026 to March 2027. As of October 20, 2026, no announcement of the opening date was found. The opening timing of Imabari IC to Imabari Asakura IC (4.6 km) has not been announced either.

The Matsuyama River and National Highway Office announced the decision on the name Imabari Asakura IC on November 11, 2025. Before that, pamphlets and other materials called it “今治朝倉IC(仮称)” (Imabari Asakura IC (tentative name)).

Location map of Imabari Road. Imabari IC to Imabari Asakura IC is 4.6 km long, and Imabari Asakura IC to Imabari Yunoura IC is the 5.7 km section scheduled to open in fiscal Reiwa 8
Source: the map part cut out from the location map in the attachment to “今治・小松自動車道 国道196号 今治道路のインターチェンジ名称を決定しました!” (the interchange name on Imabari Road has been decided), Matsuyama River and National Highway Office (November 11, Reiwa 7 (2025), PDF, in Japanese). The photos below the map were left out. The figure says “国土地理院地図を加工し作成” (made by editing a GSI map). Tap the image to open it larger.

On the effects of the road, the page of the Matsuyama River and National Highway Office says the following.

当該事業により、西瀬戸自動車道(瀬戸内しまなみ海道)と四国の高速道路 ネットワークがつながり、尾道から松山までの所要時間短縮と広域交流ネットワークが 形成され地域の活性化が期待されます。

Translation: “This project will connect the Nishiseto Expressway (Setouchi Shimanami Kaido) with Shikoku’s expressway network. It is expected to shorten the travel time from Onomichi to Matsuyama, form a wide-area exchange network, and revitalize the region.”

The same office’s pamphlet (made in November, Reiwa 7 (2025)) has a figure showing the travel time from Imabari Shintoshi (今治新都市) (District 1) to the border between Imabari City and Saijo City. It is about 20 minutes on National Route 196, and about 14 minutes after Imabari Road opens (about 6 minutes shorter). The time on National Route 196 is based on vehicle travel data for weekdays from 7:00 to 19:00 in September to November 2021. The time after opening is an estimate at the design speed of 80 km/h.

The listed sources do not cover how tolls will be treated after the opening. The current toll treatment is in the article on toll roads.

National Route 11: The Kawanoe-Mishima, Niihama and Komatsu Bypasses

The Matsuyama River and National Highway Office is building bypasses of National Route 11 in Shikokuchuo City, Niihama City and Saijo City. All three are partly open, and the timing for opening the rest is not given.

Bypass Section Length and open parts Next steps (the office’s page)
Kawanoe-Mishima Bypass Kawanoe-cho, Shikokuchuo to Nakanosho-cho 10.1 km. 3.5 km with four lanes, 3.0 km with a provisional two lanes 「未開通区間の調査設計を推進します。」 (We will push ahead with the survey and design of the unopened sections.)
Niihama Bypass Funaki, Niihama to Ojoin 9.3 km. 3.4 km with four lanes, 2.5 km with a provisional two lanes 「調査設計・用地買収を推進します。」 (We will push ahead with survey and design and land acquisition.)
Komatsu Bypass Komatsu-cho Shinyashiki, Saijo to Yasui 7.5 km. 2.4 km with a provisional two lanes 「調査設計・用地買収を推進します。」 (We will push ahead with survey and design and land acquisition.)

Part of the Niihama Bypass opened on April 27, 2024. In an August 18, 2025 announcement by the Matsuyama River and National Highway Office, traffic on the bypass one year after the opening was about 11,900 vehicles a day on weekdays. The office says the travel speed on the parallel National Route 11 (the existing road section) rose by up to about 12 km/h in the same time periods compared with before the opening.

Chuyo: The Matsuyama Outer Ring Road and the Four-Lane Widening of the Matsuyama Expressway

Matsuyama Outer Ring Road: The Rest of the Airport Line and the Interchange East Line Are Under Construction or Under Way

The Matsuyama Outer Ring Road connects Matsuyama IC with Matsuyama Airport, Matsuyama Port and other places. MLIT, Ehime Prefecture and Matsuyama City are building it. In the Matsuyama River and National Highway Office’s pamphlet (made in February, Reiwa 6 (2024)) and the prefecture’s “愛媛の道路2025” (Ehime’s Roads 2025), it is divided into the following three sections.

  • Interchange Line (インター線) (National Route 33 to National Route 56, 4.8 km): open
  • Airport Line (National Route 56 to the Matsuyama Airport Line (a major local road), 3.8 km): the 3.2 km of side roads and the motorway section from Yogominami IC to Higashi-Habu IC (2.4 km, opened on February 24, 2024) are open
  • Interchange East Line (National Route 33 to National Route 11, 2.0 km): project under way

The length of the Interchange East Line is 2.0 km in the national pamphlet and the prefecture’s “愛媛の道路2025,” and “国道11号から松山ジャンクション間(2.5km)” (between National Route 11 and Matsuyama Junction (2.5 km)) on the prefecture’s page on regional high-standard roads (updated in August 2023).

The rest of the Airport Line is under construction. The Matsuyama River and National Highway Office had announced that it would hold a tour of the bridge work on October 7, 2026, at the Airport Line construction site in Minamiyoshida-machi, Matsuyama. The opening timing of the rest of the Airport Line and of the Interchange East Line has not been announced. The section north of Matsuyama Airport to National Route 196 is labeled “調査中区間” (section under study) in the figure in the prefecture’s pamphlet.

Figure of the Matsuyama Outer Ring Road: Airport Line 3.8 km, Interchange Line 4.8 km, Interchange East Line 2.0 km, and the 2.4 km opened on February 24, Reiwa 6 (2024)
Source: page 2 of the PDF (booklet pages 1 to 2) of the “松山外環状道路” (Matsuyama Outer Ring Road) pamphlet, Matsuyama River and National Highway Office (made in February, Reiwa 6 (2024), PDF, in Japanese). The map says “電子地形図25000(国土地理院)を加工して作成” (made by editing the GSI Digital Topographic Map 25000). Tap the image to open it larger.

On the effects of the opened sections, the national government and the prefecture give the following numbers.

  • Matsuyama River and National Highway Office (announcement of June 26, 2025): one year after the opening of Yogominami IC to Higashi-Habu IC on the Airport Line, the travel time between Matsuyama IC and Matsuyama Airport went from about 28 minutes to about 13 minutes.
  • Ehime Prefecture (“愛媛の道路2025”): with the opening of the Interchange Line and the Airport Line and other work, the travel time between Matsuyama Airport and Matsuyama IC is about 15 minutes shorter. The figure on the same page says “整備なし 約28分” (without the roads, about 28 minutes), “整備あり 約12分” (with the roads, about 12 minutes) and “約17分短縮” (about 17 minutes shorter). The figure does not say how far the roads would be built for these numbers.

The national government’s about 13 minutes and the prefecture’s about 15 minutes shorter are both official numbers.

Four-Lane Widening of the Matsuyama Expressway: 6.3 km of Iyo IC to Uchiko-Ikazaki IC Was Completed in 2025

Between Matsuyama IC and Ozu IC, the Matsuyama Expressway has sections with a provisional two lanes, where the inbound and outbound lanes are not separated. The prefecture’s “愛媛の道路2025” says the following.

「松山IC~大洲IC」間の暫定2車線区間(約38.1km)のうち、これまでに計25.7kmが事業化されており、そのうち、「伊予IC~内子五十崎IC」間の一部(6.3km)が令和7年4月19日に完成しました。

Translation: “Of the provisional two-lane sections (about 38.1 km) between Matsuyama IC and Ozu IC, a total of 25.7 km has been approved as projects so far. Of this, part of the section between Iyo IC and Uchiko-Ikazaki IC (6.3 km) was completed on April 19, Reiwa 7 (2025).”

The completed 6.3 km runs from Futami-cho Kaminada, Iyo to Miaki, Iyo (NEXCO West Japan’s announcement of March 26, 2025). On NEXCO West Japan’s project page, the remaining work is the following three sections. The construction start rates as of the end of August 2026 are the numbers on the project page.

Section Construction start rate (end of August 2026) What the project page says
About 4.4 km between Uchiko-Ikazaki IC and Ozu IC 100% Construction is under way
About 9.7 km between Iyo IC and Uchiko-Ikazaki IC 31% Surveys, design and construction are under way
About 5.3 km between Iyo IC and Uchiko-Ikazaki IC 0% Surveys and design are under way

The completion timing of the remaining sections has not been announced.

Nanyo: The Ozu-Yawatahama Expressway, Tsushima Road and the Sukumo-Uchiumi Road

Ozu-Yawatahama Expressway: Yoruhiru Road and Ozu-Nishi Road Are Being Built

The Ozu-Yawatahama Expressway is a motorway of about 14 km that connects Yawatahama City and Ozu City. Ehime Prefecture is building it. In the prefecture’s pamphlet, it is a free motorway. The page of the prefecture’s Nanyo Regional Office (updated on September 11, 2026) says the following.

本自動車道は、愛媛県に3つある高規格道路のミッシングリンクの一つで、平成9年度から、名坂道路(平成25年3月開通)、八幡浜道路(令和5年3月開通)、夜昼道路、大洲西道路の4つの工区に分けて整備を進めています。

Translation: “This expressway is one of the three missing links of high-standard roads in Ehime Prefecture. Since fiscal Heisei 9 (1997), it has been built in four sections: Nasaka Road (opened in March, Heisei 25 (2013)), Yawatahama Road (opened in March, Reiwa 5 (2023)), Yoruhiru Road and Ozu-Nishi Road.”

Section Between Length Stage
Nasaka Road (名坂道路) Honai IC (保内IC) to Yawatahama IC (八幡浜IC) 2.3 km Opened on March 17, 2013
Yawatahama Road (八幡浜道路) Yawatahama IC to Yawatahama East IC 3.8 km Opened on March 25, 2023
Yoruhiru Road Yawatahama East IC to Ozu-Hirano IC (大洲平野IC) (Go, Yawatahama to Hirano, Ozu) 4.2 km Being built. Includes the Shin-Yoruhiru Tunnel (新夜昼トンネル) (2,690 m) and other work
Ozu-Nishi Road Ozu-Hirano IC to Ozu-Kitatada JCT (tentative name) (大洲北只JCT(仮称)) (Hirano to Kitatada, Ozu) 3.3 km Being built. The figure in the pamphlet says “大洲西道路の区間は現在設計中です。” (The Ozu-Nishi Road section is now being designed.)

The prefecture has published photos of the Yoruhiru Road construction as of September 2, 2026 (near Yawatahama East IC and near Ozu-Hirano IC). The opening timing of Yoruhiru Road and Ozu-Nishi Road is not given on the prefecture’s page or in the pamphlet.

Location map of the Ozu-Yawatahama Expressway. Nasaka Road and Yawatahama Road are opened sections, and Yoruhiru Road and Ozu-Nishi Road are being built
Source: the location map cut out from page 2 of the “大洲・八幡浜自動車道パンフレット” (Ozu-Yawatahama Expressway pamphlet), Ehime Prefecture (PDF, in Japanese). The base of the map is an aerial photo taken by the GSI (taken in 2014). Tap the image to open it larger.

Tsushima Road: The Shin-Uchiumi Tunnel (Tentative Name) Broke Through on October 15, 2026

Tsushima Road is a motorway of about 10.3 km from Tsushima-Iwamatsu IC on Uwajima Road to Uchiumi IC (tentative name) in Ainan Town. The Ozu River and National Highway Office is building it, and the project was approved in fiscal 2012. On the prefecture’s page, it is a free motorway (two lanes when completed).

On October 16, 2026, the Ozu River and National Highway Office announced that the Shin-Uchiumi Tunnel (tentative name) (新内海トンネル(仮称)) broke through on October 15. The construction site is Kashiwa, Ainan to Tsushima-cho Kamihataji, Uwajima, and the tunnel is 2,541 m long. Neither this announcement nor the office’s page gives the opening timing of Tsushima Road.

The office’s pamphlet describes the effects of the road as follows.

松山から南予地域に向けて広域交通ネットワークが整備されることにより、愛媛県庁~愛南町役場間は、国道56号を利用する場合に比べて最大80分短縮されます。

Translation: “With a wide-area transport network built from Matsuyama toward the Nanyo region, the trip between the Ehime Prefectural Office and the Ainan Town Office will be up to 80 minutes shorter than when using National Route 56.”

In the same figure, from the Ehime Prefectural Office to the Ainan Town Office takes 3 hours 24 minutes without expressways, 2 hours 12 minutes using the expressway from Matsuyama IC to Tsushima-Iwamatsu IC (72 minutes shorter), 2 hours 06 minutes using it from Matsuyama IC to Uchiumi IC (tentative name) (78 minutes shorter), and 2 hours 02 minutes using it to Johen IC (tentative name) (城辺IC(仮称)) on the Sukumo-Uchiumi Road (82 minutes shorter). The sections under construction are estimates calculated at 70 km/h. The pamphlet also says that because Tsushima Road is a motorway, pedestrians, bicycles, motorcycles of 125 cc or less, mopeds and others cannot use it.

Sukumo-Uchiumi Road: The Whole Route Was Approved as a Project in Fiscal 2024

The Sukumo-Uchiumi Road is a 29.2 km motorway that connects Sukumo-Wada IC in Kochi Prefecture and Uchiumi IC (tentative name) in Ainan Town. The prefecture’s page says it forms part of the Shikoku 8-shaped Network together with Tsushima Road. The prefecture’s page describes the project approval as follows.

2022(R4)年度に(仮称)宿毛新港IC~(仮称)一本松IC(4.7km)と(仮称)御荘IC~(仮称)内海IC(7.6km)が、2024(R6)年度に(仮称)一本松IC~(仮称)御荘IC(9.8km)が事業化され、国土交通省により整備が進められています。

Translation: “In fiscal 2022 (R4), Sukumo Shinko IC (tentative name) to Ipponmatsu IC (tentative name) (4.7 km) and Misho IC (tentative name) to Uchiumi IC (tentative name) (7.6 km) were approved as projects, and in fiscal 2024 (R6), Ipponmatsu IC (tentative name) to Misho IC (tentative name) (9.8 km) was approved. The Ministry of Land, Infrastructure, Transport and Tourism is building them.”

In the Ozu River and National Highway Office’s Tsushima Road pamphlet, the Sukumo-Uchiumi Road (29.2 km long) is “令和6年度全線事業化” (whole route approved as a project in fiscal Reiwa 6 (fiscal 2024)). On July 30, 2024, the office had announced that it would hold the first briefing on entering land since the project approval, for the section between Ipponmatsu and Misho. The opening timing has not been announced.

Sections Opened (2025 to 2026)

From January 2025 to October 20, 2026, the only section in Ehime Prefecture confirmed in official sources as opened or completed is the following one.

Date Road Section What changed Source
Saturday, April 19, 2025, 6:00 Matsuyama Expressway 6.3 km between Iyo IC and Uchiko-Ikazaki IC (Futami-cho Kaminada to Miaki, Iyo) From a provisional two lanes to four lanes NEXCO West Japan’s announcement, Ehime Prefecture’s “愛媛の道路2025”

Before that, in 2024, Yogominami IC to Higashi-Habu IC on the Matsuyama Outer Ring Road Airport Line (2.4 km, February 24) and part of the National Route 11 Niihama Bypass (April 27) opened. The numbers one year after the openings are in the Toyo and Chuyo sections above.

Not covered in this article

  • The opening date of Imabari Asakura IC to Imabari Yunoura IC on Imabari Road. The opening timing of Imabari IC to Imabari Asakura IC, and how tolls will be treated after the opening.
  • The opening or completion timing of the rest of the Matsuyama Outer Ring Road Airport Line and the Interchange East Line, Yoruhiru Road and Ozu-Nishi Road on the Ozu-Yawatahama Expressway, Tsushima Road, the Sukumo-Uchiumi Road, the three bypasses on National Route 11, and the remaining four-lane widening of the Matsuyama Expressway.
  • Other sections that opened in 2025 to 2026. The prefecture’s “主要道路開通情報” (major road opening information) was updated on August 21, 2024, and the newest entry is Yawatahama Road in March 2023. This article does not cover roads built by cities and towns.
  • The documents of the national government’s project evaluations (re-evaluations by the Shikoku Regional Development Bureau’s project evaluation monitoring committee, fiscal 2022 to 2024) also do not give target fiscal years for completion of Imabari Road, the three bypasses on National Route 11, the Matsuyama Outer Ring Road, Tsushima Road or the Sukumo-Uchiumi Road.

Night closures and changes to the layout of entrances and exits in sections under construction are announced each time by each office and NEXCO West Japan. How to check before you leave is in the article on road information.

Sources